Should have been lifted into place yesterday but the crane was too heavy for the base put down. The TV cameras etc were waiting ready to film this.

Section by section completion of the Chesterfield canal.

https://chesterfield-canal-trust.org.uk/restoration/new-restoration-sections/

8 Comments

  1. I wasted a day off work (Renishaw Hall Gardens) to go watch that, but at least I took my cross stitch pic of my workplace, and scanner to listen to air traffic control to kill the time waiting.

  2. Nice vlog Tim, I walked to Chesterfield down trans Pennine trail last year to walk down side of canal and wondered what all the work was for and now I know. Cheers mate.

  3. At the end of Bell house Lane is where this phase of restoration ends……so there’s a few thousand of ton of clay to be moved towards the Puddlebank…..a new lock to be built just past the old railway line and a new bridge at the end of Bell house Lane for the farm access…The next stage will be interesting…..new aquaduct